Donate SIGN UP

Upgrade Central Heating System - Combi Boiler.

Avatar Image
Oakleaf51 | 17:38 Fri 18th Apr 2008 | Home & Garden
1 Answers
Estimate recieved �3193. Breaks down as follows:-
(using existing eight radiators in the house).
Worcester condensing boiler, flue kit, wall jig �1189.88.
Full conditioning powerflush �250.
T.R.V.'s and control update �256.32.
Pipework & fittings �87.55.
Meter wall plate �22.
Notification to Worcester & Corgi validations �12
3 Days labour �900
-----------------------------------------------------------------------------
Parts sub total �1817.75
Labour sub total �900.
VAT �475.61
Total �3193.36

So my question is, is this estimate reasonable or too high? I am out of work at present and only have fixed savings and small pension so money is tight.
Gravatar

Answers

Only 1 answerrss feed

Best Answer

No best answer has yet been selected by Oakleaf51. Once a best answer has been selected, it will be shown here.

For more on marking an answer as the "Best Answer", please visit our FAQ.
It depends where you are as to labour costs. I typicaly charge �200 a day, and it only costs �5 to register the boiler with CORGI and it is free to register it with Worcestor. The materials price list is compeatively priced so they are not ripping you off with those. Try getting another couple of quotes as this ones labour charges seem high.

Only 1 answerrss feed

Do you know the answer?

Upgrade Central Heating System - Combi Boiler.

Answer Question >>

Related Questions

Sorry, we can't find any related questions. Try using the search bar at the top of the page to search for some keywords, or choose a topic and submit your own question.