My mother-in-law has bought a flat which needs completely refurbishing ie. New kitchen, new bathroom & toilet with re-tiling, new carpets and redecorating ( wallpapering and painting)
What is the best order in which to have these things done ?
Strip out old kitchen and bathroom
Redo plumbing with bathroom and any pipe changes needed in kitchen
Refit kitchen
Refit bathroom sanitaryware
Tiling
Painting
Wallpapering
Carpets
Sequence might have to vary if she's living in it during all this.